Tojo Mushroom was looking to save costs and reduce their carbon footprint.
Energy Efficient Technologies performed a detailed energy audit, made numerous recommendations for improvements.
The purpose of this case study is to provide the results of the savings validation pilot of an HVAC and refrigeration ECM now known as CryoGenX4 at the largest mushroom growing facility in the US
Operation of the Mushroom House
Each HVAC unit used for conditioning the mushroom house operates on a unique schedule of set points, percentage of outside air, backup A/C, and heat at 100% while A/C is on. This schedule is important as the operation of the equipment affect the results of the test.
Data Analysis
The data was analyzed by gathering the operation schedule of each unit and categorizing similar settings of set point, outside air percentage, and outside temperature. Using multiple similar days the percentage of savings before and after were created and averaged to present a final value.
Other Food Manufacturing Case Studies:
HVAC Optimization, Now in its 4th patented generation called CryoGenX4, was validated in two stores. Total system efficiency across all five units improved by an average of 29%, while the EER across...
Summary Results The demonstration was a success as the units now provide colder supply air with greater efficiency due to the restoration of the heat transfer ability of the evaporator and condenser...
Keeping it Cold Premier Distribution Company (PDC) and Anheuser-Busch need to keep their product cold, and stored at a consistent level. The surrounding desert atmosphere was another factor that...
Energy Efficient Technologies
400 East Pratt Street, Suite 800
Baltimore, MD 21202
800-344-8132 (Office)